On September 7th, 2011 Baltic Container Terminal entered into a contract No. L-JPR-11-0104 with v / a Latvian Investment and Development Agency regarding the implementation of the Project “Container Automatic Management System (rail and quay modules)”, co-financed by the European Regional Development Fund.

 

 

Investing in Your Future!

 

Project finished works and works-in-progress until March 7th, 2011:



Worked out the project technical documentation;

Received all approvals required for the project;

Completed project communication systems;

Completed mounting of the railway portal constructions;

Completed installation of the railway portal equipment;

Completed installation of the servers;

Completed installation of data storage equipment;

Received all equipment and licenses;

Completed construction works and cable-laying;

Installed and adjusted all the facilities;

Installed and adjusted the computerized control unit;

Started training process;

Getting ready for testing of the service modules.

 

On May 31st, 2012 all intended works within the project have been completed.

 

On June 6th, 2012 the result of the Project implementation - the object “Container Automatic Management System (rail and quay modules)” - has been put into operation.